EASTERN MARKET REHABILITATION - 4-Week Look Ahead
Thursday, September 25th, 2008
4-Week Look Ahead
A) Previous Week Beginning Monday, September 15, 2008
Ø Pressurize HVAC/Heating Piping, North Hall (C)
Ø Continue Arch Shoring, Basement (South End) (C)
Ø Complete Backfilling @ Underpinning (C)
Ø Began Concrete Floor Slab Demo, South Hall (A) (IP)
B) Week Beginning Monday, September 22, 2008
Ø Continue Site Utilities, South Hall (IP)
Ø Continue Sewage Connection Test Pit at “C” Street (IP)
Ø Continue Site Utilities, East Side, North Hall (IP)
Ø Continue Under Slab Electrical, North Hall (IP)
Ø Continue Concrete Floor Slab Demo, South Hall (IP)
Ø Begin Steel Beam Joint Survey/Review
Ø Begin to work Mock-ups for Concrete Stamping
Ø Remove Spoils/Rocks, North and Center Hall
C) Week Beginning Monday, September 29, 2008
Ø Begin Door Rehab/Removal
Ø Continue Site Utilities
Ø After Joint Survey, Begin Steel Beam Repair/Replacement
Ø Begin Under-slab Plumbing, Center Hall
Ø Begin Work on Kiosk and Elevator Areaway
D) Week Beginning Monday, October 6, 2008
Ø Complete Site Utilities, as required
Ø Start Roof/Skylight Repairs
Ø Install Floor Drains, Sinks, Sleeves, South Hall
Ø Continue Steel Beam Repair/Replacement
Ø Continue Door/Window Rehab
Ø Continue Work on Kiosk and Elevator Areaway
E) Week Beginning Monday, October 13, 2008
Ø Continue Door Rehab/Removal
Ø Continue Roof/Skylight Repairs
Ø Continue Steel Beam Replacement
Ø Continue to Install Floor Drains, Sinks, Sleeves, South Hall
Ø Pour Concrete Floor Slab, South Hall
LEGEND: (S) Started; (C) Completed; (IP) In Process; (NS/D) Not Started or Delayed; (A) Add Item