EASTERN MARKET REHABILITATION Contstruction Schedule
Monday October 20, 2008
EASTERN MARKET REHABILITATION
4-Week Look Ahead
A) Previous Week Beginning Monday, October 13, 2008
Ø Continue Steel Beam Joint Survey, 3rd Review; Tues, Oct 14 (C)
Ø Complete Removal of Spoils/Rocks, North and Center Hall (C)
Ø Continue Site Utilities, East Side (C)
Ø Complete Top of Brick Arch Survey, North and South Ends (C)
Ø Continue Concrete Work on Kiosks; Must Strip Forms (C)
B) Week Beginning Monday, October 20, 2008
Ø Install Cast Iron Pipe Boots for Down Spouts
Ø Install Last Section of D.I. Pipes
Ø Repair Wrought Iron Fence/Gate at Hair Salon
Ø Continue Steel Beam Replacement (IP)
Ø Complete Site Utilities, as required (IP)
Ø Begin CMU Work on Kiosks
Ø Pour Exterior Concrete Slabs, East and West Sides
Ø Start Excavation for Elevator Pit
Ø Begin Door and Frame Survey/Removal
Ø Continue Structural Carpentry; Dormer/Wall Framing Center Hall (IP)
Ø Begin Center Hall Rehab (Carpentry and Steel Support for HVAC)
Ø Begin Electrical Rough-Ins, Center and North Hall
C) Week Beginning Monday, October 27, 2008
Ø Continue Electrical Rough-Ins, Center and North Hall
Ø Continue Structural Carpentry; Dormer/Wall Framing Center Hall (IP)
Ø Begin Brick Paver Installation
Ø Begin Skylight Repairs, Center Hall
Ø Continue Door Rehab
Ø Continue Steel Beam Repair/Replacement
Ø Continue Work on Kiosks, as required
D) Week Beginning Monday, November 3, 2008
Ø Continue Brick Paver Installation
Ø Continue Skylight Repairs, Center Hall
Ø Continue Steel Beam Repair/Replacement
Ø Continue Door/Rehab
Ø Install Floor Drains, Sinks, Sleeves, South Hall (NS/D; Depends on decision about South Hall Floor System)
E) Week Beginning Monday, November 10, 2008
Ø Continue Steel Beam Repair/Replacement
Ø Continue Door/Rehab
Ø Continue Installation of Floor Drains, Sinks, Sleeves, South Hall (Depends on Decision about South Hall Floor System)
Ø Begin Concrete Floor Slab, South Hall; Depends on decision about South Hall Floor System)