EASTERN MARKET REHABILITATION Contstruction Schedule

Monday October 20, 2008

 

EASTERN MARKET REHABILITATION

4-Week Look Ahead

 

 

 

A)        Previous Week Beginning Monday, October 13, 2008

 

Ø      Continue Steel Beam Joint Survey, 3rd Review; Tues, Oct 14 (C)

 

Ø      Complete Removal of Spoils/Rocks, North and Center Hall (C)

 

Ø      Continue Site Utilities, East Side (C)

 

Ø      Complete Top of Brick Arch Survey, North and South Ends (C)

 

Ø      Continue Concrete Work on Kiosks; Must Strip Forms (C)

 

 

B)        Week Beginning Monday, October 20, 2008

 

Ø      Install Cast Iron Pipe Boots for Down Spouts

 

Ø      Install Last Section of D.I. Pipes

 

Ø      Repair Wrought Iron Fence/Gate at Hair Salon

 

Ø      Continue Steel Beam Replacement (IP)

 

Ø      Complete Site Utilities, as required (IP)

 

Ø      Begin CMU Work on Kiosks

 

Ø      Pour Exterior Concrete Slabs, East and West Sides

 

Ø      Start Excavation for Elevator Pit

 

Ø      Begin Door and Frame Survey/Removal

 

Ø      Continue Structural Carpentry; Dormer/Wall Framing Center Hall (IP)

 

Ø      Begin Center Hall Rehab (Carpentry and Steel Support for HVAC)

 

Ø      Begin Electrical Rough-Ins, Center and North Hall

 

 

C)        Week Beginning Monday, October 27, 2008

 

Ø      Continue Electrical Rough-Ins, Center and North Hall

 

Ø      Continue Structural Carpentry; Dormer/Wall Framing Center Hall (IP)

 

Ø      Begin Brick Paver Installation

 

Ø      Begin Skylight Repairs, Center Hall

 

Ø      Continue Door Rehab

 

Ø      Continue Steel Beam Repair/Replacement

 

Ø      Continue Work on Kiosks, as required

 

 

D)        Week Beginning Monday, November 3, 2008

 

Ø      Continue Brick Paver Installation

 

Ø      Continue Skylight Repairs, Center Hall

 

Ø      Continue Steel Beam Repair/Replacement

 

Ø      Continue Door/Rehab

 

Ø      Install Floor Drains, Sinks, Sleeves, South Hall (NS/D; Depends on decision about South Hall Floor System)

 

 

E)        Week Beginning Monday, November 10, 2008

 

Ø      Continue Steel Beam Repair/Replacement

 

Ø      Continue Door/Rehab

 

Ø      Continue Installation of Floor Drains, Sinks, Sleeves, South Hall (Depends on Decision about South Hall Floor System)

 

Ø      Begin Concrete Floor Slab, South Hall; Depends on decision about South Hall Floor System)